Question
Hello:

What is a simple solution to the following?

If 20 men can paint 5 houses in 10 days, how many days can 40 men paint 15 houses?

40 men is 2 X 20 men; 15 days is 3 X 5 houses. Is there a solution using this information to determine the answer for how many days?

I thank you for your reply.

Answer
20 men can paint 5 houses in 10 days so that is 4 houses every 10 days per man. At that rate 40 men can paint twice as many houses in twice as many days,  i.e.  40 men can paint 10 houses in 10 days. But we need to paint 15 houses so it will take another 5 days to accomplish the feat.  

Advanced Math

All Answers


Answers by Expert:


Ask Experts

Volunteer


Sombra Shadow

Expertise

I can answer most questions up through Calculus and some in Number Theory and Abstract Algebra.

Experience

I have had my Bachelor's Degree since 1987 and have been a teacher since 1988. I earned my Masters Degree in Mathematics May 2010. I have been teaching at the same community college since 2002.

Education/Credentials
I have taught 12 years at the community college level, medical college, and technical college as well as a high school instructor and alternative education instructor and charter school instructor.

Awards and Honors
Master's GPA 3.56 Bachelor's GPA 3.34 Post grad work not degree related GPA 4.0

©2016 About.com. All rights reserved.