QuestionHi,
I've created subprojects under a master project. However, on some subprojects the start date is not displayed instead I get ####### in the start date field. On others, the dates appear fine.
Thanks in advance,
Safi
AnswerGetting the ##### indicates the column is not wide enough for the date. You need to either reformat the dates or widen the column. The reason why some dates might appear while others are too big is because of formatting, 1/1/03 is shorter then 12/31/03.
Hope this helps,
Scott<>