Civil Engineering/pad foundation

Advertisement


Question
hi..
can u please tell me the methodology of pad foundation construction?
I'll be grateful if u can explain it to me..
thank you..
Ain

Answer
Hi Ain,

Here are the steps

1. Read the drawing and get the dimensions of the footing.
2. Excavate and prepare the surface as per the drawings, e.g. you may be required to compact the soil.
3. Put the form work as per the dimensions of the footing.
4. Get the reinforcement (rebars) and put them as per the drawings. you may need to tie them up.
5. Do not forget to put the chairs to maintain sufficient cover(Gap) from the ground.

you are ready with the reinforcement placement and now you can pour the concrete evenly.

Hope this helps and Let me know if you have any more questions.

Thanks and regards
Veto

Civil Engineering

All Answers


Answers by Expert:


Ask Experts

Volunteer


Veto Varma

Expertise

I can answer questions related to design and analysis of structures. I have experience in design and detailing of concrete and steel structures. I can answer your queries related to practical difficulties in design and construction. I also have several years of experience in seismic design and retrofitting.

Experience

I have been working in the Area of structural design and seismic engineering. Presently I am a consulting structural engineer in Saskatchewan, Canada. You can ask questions related to Industrial and Building structures. Education: Masters in Structural Engineering Publications: More than 14 publications in reputed journals and conference proceedings related to structural engineering.

©2012 About.com, a part of The New York Times Company. All rights reserved.