You are here:

Civil Engineering/Industrial building slab strength

Advertisement


Question
QUESTION: I am working on a project to move a number of separate business units to a single site. The site is already built and need to verify that the existing concrete slab is strong enough to take the weight of the injection moulding machines to be moved there.

The machine characteristics are:
Maximum weight = 6150Kg
Number of feet = 6
Size of each foot = 150mm dia

Can you tell me what the kN/m2 I need the concrete slab to be able to take please?
And also what would be the minimum specification of concrete I would need the building to have to support this weight of machine?

Many thanks in advance.

ANSWER: Hi Rex,

If the weight is evenly distributed amongst the 6 feet, then the static pressure under each foot is around 0.5 N/mm2, which any good concrete will be able to support. However, whether the floor slab is good enough depends much on the quality of the supporting ground, as well as on the thickness of the slab and the amount/location of the rebar.

Assuming that the slab is 200mm thick, then the ground immediately below should be able to safely bear a pressure of around 150-200 kN/m2 to avoid any settlement or distress to the concrete.

All this assumes that there is no dynamic loading, as this will increase all the loading/pressure figures.

---------- FOLLOW-UP ----------

QUESTION: Thank you for your 1st reply and since asking that question I've been given a little bit more detail about the location. They are:
Core sample detail:
0-165mm Reinforced concrete floor slab with no steel reinforcements found
165mm Visqueen
165-300mm Crushed rock (No fines)
300-580mm Brown silty sand
580-1100mm Light brown sand

Also the machine stands on 6 feet that are positioned in 2 rows of 3 down each side of the machine evenly positioned over a 4m length and the rows being 0.75m apart.

Many thanks,

Rex

ANSWER: Hi Rex,

If the slab is only 165mm thick, then the subgrade will need to support more than 200 kN/m2. Without knowing the standard of compaction, etc, the only way that you can determine capacity is to do a test loading of 1000 kg over an isolated plate of 150mm diameter and see how the slab behaves over 24 hours.

---------- FOLLOW-UP ----------

QUESTION: Thank you for a fast response once again.

The slab has been in place for over 20 years I believe so would it be fair to assume that the subgrade will by now be very compact? Or is that a naive question?

If the subgrade is compact would the slab be OK for the weight of machines I have please?

Many thanks, Rex

Answer
Hi Rex,

Yes, your assumption could be correct, but this depends on the loading the slab has been subjected to. Normally the maximum load in a warehouse would be about 7.5-10 kN/m2, but you are applying a pressure (localised) of between 200-400 kN/m2, so as you will appreciate there is a big difference!

You could mitigate the potential problems by using steel spreader beams under the feet, if that is practical.

Civil Engineering

All Answers


Answers by Expert:


Ask Experts

Volunteer


Arshad Khan

Expertise

I can answer any questions to do with civil and structural engineering consultancy and construction industry in East Africa and the Middle East, and specifically with the analysis and design of reinforced concrete structures. My particular expertise is in the aseismic design and optimisation of tall buildings.

Experience

Employment history: 36 years in Construction and consultancy in the UK, Kenya, Tanzania, Uganda, Ethiopia, Eritrea, South Africa, Somalia, Zambia, Austria, Bahrain, Kuwait, Doha and the U.A.E.

Organizations
.Fellow of Institution of Structural Engineers (UK) .Fellow of Institution of Civil Engineers(UK) .Member of the Institution of Engineers, Kenya .Registered Engineer, ERB, Kenya .Member of the Architectural Association of Kenya (Engineers Chapter) .Chartered Engineer (UK)

Publications
•1984: International Conference on the Art and Practice of Structural Design, London •1994: 3rd Int. Kerensky Conference in Structural Engineering, Singapore •2008: International Conference on High-Rise Towers, Abu Dhabi

Education/Credentials
BSc, 1st Class Hons, in Building Engineering, University of Bath, UK MSc in Concrete Structures and Technology, University of London. Diploma of Imperial College, UK.

Awards and Honors
•Science Congress Special Award (for 2-seater Hovercraft - 1968) •Institution of Civil Engineers Award for outstanding performance at Bath University (1975) •Concrete Society Postgraduate study Bursary Award (1976) •Consular Representative for British High Commission, Nairobi. (1995 to 1998) •Examiner for Institution of Civil Engineers Professional Interviews, Nairobi. (1997 to 1998) •Branch Representative in Vienna for PI assessment for Inst. of Struct. Engrs. (1999 to date)

©2012 About.com, a part of The New York Times Company. All rights reserved.