Construction Industry/Breech of Contract

Advertisement


Question
Hi,
is it possible to short list the cases to be considered for breaching  the contract by contractor

i have a case now the contractor has sign a supplementry agreement with client due to slowing down the progress as requested by client and now the contractor is in delay from his side as per the update for revised clause 14 programme of work agreed withe supplementary aggrement and he is lacking to submit revised catch up  programme as requested by client ,

the client is forcing the engineer to record this case as breech to the contract

pleaseadvise

Answer
Dear Ahmad,

As a short and preliminary answer to your question, the situation you described seems to be as you name it: a breach of contract.
Wether it will stand or not in front of an adjudicator, depends on the particular circumstances.
By the way, what does your contract provide for disputes adjudication?

If you are interested in continuing our conversation, please use my personal address: etraista@yahoo.co.uk

Kind regards,
Emilian

Construction Industry

All Answers


Answers by Expert:


Ask Experts

Volunteer


Emilian TRAISTA

Expertise

I can answer any question regarding FIDIC Conditions of Contract.

Experience

Roads and Motorways (New or Rehabilitation of existing): Resident Engineer - 7 years Roads and Motorways (New or Rehabilitation of existing): Project Manager - 3 years

Organizations
Romanian Association of Consulting Engineer

Education/Credentials
Technical University - Iasi, Romania

Past/Present Clients
Romanian National Company of Motorways and National Roads Municipality of Bucharest, Romania

©2012 About.com, a part of The New York Times Company. All rights reserved.