Question
What is the normal time for R.C.C curing? Why it is normally presumed that the concrete slab surface should be dried up before de-shuttering?

Answer
Dear Sushil
concrete curing is required during the first 7 days. this is the period where concrete chemical reaction produce most of the strength of concrete. I don't understand what do you mean by dried up but you should not remove the shuttering before the said 7 days and make sure that the design accepts about 70% OF THE CONCRETE STRENGTH based on what live / dead load you have during construction
cheers

Construction Industry

All Answers


Answers by Expert:


Ask Experts

Volunteer


Wael Ghadban

Expertise

Will respond to queries related to Engineering Contracts subject to FIDIC or other Conditions, tendering and contracting, project management, residential and commercial construction, and general Civil Engineering questions. Can answer most questions related to aviation and airports as related to the Airports, Facility management.

Experience

Project construction, Projects Management,Civil Aviation, Airports construction and operation, Airport Pavement Design, Major Residential and commercial construction. Contract Management, FIDC, All Types of Contracts. ICAO, UFC, and FAA regulation and standards

Education/Credentials
MSc Civil Engineering

©2016 About.com. All rights reserved.