First response to queries regarding extensions of time, variations orders, site instructions and payment using FIDIC and other forms of Conditions of Contract, based on English Law, and derivatives only.

Experience
Value . . .
It's unwise to pay too much, but it's unwise to pay too little. When you pay too much you lose a little money, that is all. When you pay too little, you sometimes lose everything, because the thing you bought was incapable of doing the thing you bought it to do.
The common law of business balance prohibits paying a little and getting a lot. It can't be done. If you deal with the lowest bidder, it's well to add something for the risk you run.
And if you do that, you will have enough to pay for something better.
. . . John Ruskin (1819 - 1900)
"We are too poor to buy something cheap"
.Romanian Proverb 2002
A lean compromise is better than a fat lawsuit. George Herbert (English poet 1593-1633)
I said it in Hebrew, I said it in Dutch,
I said it in German and Greek:
But I wholly forgot (and it vexes me much)
That English is what you speak!" Hunting of the Snark - Lewis Caroll
Match your presentation to the reader!
The joy of food lasts but an hour, of sleep but a day, of a woman, but a month, but the joy of a building lasts a lifetime. Syrian proverb.
Comments and observations leading to improvements in the translation of FIDIC Red & Yellow books into Romanian prior to approval by FIDIC (reference 'Preface to the Romanian edition')

   

You are here:  Experts > Industry > Construction Industry > Construction Law

SubjectDate AskedExpert

Time at large2/9/2010John Dowse
  Q: I am currently administering a contract where the circumstances are as follows: 1. Contract has two ...
  A: In view of the lack of knowledge I have of your situation and the limited information that it is ...
Claim / Compensation2/7/2010Alina Valentina Oprea
  Q: We are presently constructing a jetty at dhaka , bangladesh.In the bank protection work we have been ...
  A: In the case presented it is about the lack of access and possession of site, which caused delays and ...
Variation2/7/2010John Dowse
  Q: In a tender drawing the length of a tunnel was 150 meter, but when the construction drawing issued ...
  A: As is often the case with questions I receive, there is information missing which would be desirable ...
Variation2/7/2010Peter M. Elliott
  Q: In a tender drawing the length of a tunnel was 150 meter, but when the construction drawing issued ...
  A: There is no need for a variation order, just because the quantities have increased, under the FIDIC ...
Variation in work2/7/2010Alina Valentina Oprea
  Q: In a tender drawing the length of a tunnel was 150 meter, but when the construction drawing issued ...
  A: Once the Consultant issued the drawings showing a tunnel on 300 m instead of a tunnel of 150 m as ...
Time at large2/7/2010John Dowse
  Q: I am currently administering a contract where the circumstances are as follows: 1. Contract has two ...
  A: It is clear from your narrative that the situation is quite complex and it is possible that it is ...
difference between Advance payment and Downpayment2/7/2010Florin NICULESCU
  Q: What is the difference between Advance payment and down payment in construction Industry. Regards ...
  A: You did not specify what type of Conditions of Contract are you using, but in principle, they should ...
contractual issue2/6/2010senthilkumar sellamuthu
  Q: We signed a contract with the client in U.A.E. directly without a specification from their side and ...
  A: Unni, Thanks for your Question. Your Questions not clear. Check with your conditions of contracts ...
Breeching of Contract2/6/2010Florin NICULESCU
  Q: Is it possible to short list the cases to be considered for breaching the contract by contractor I ...
  A: Concerning first request, I am afraid that would exceed limits of this site, as answer would require ...
Issue of Instructions2/5/2010Peter M. Elliott
  Q: My Contract is FIDIC "Red" 1999 version. I have submitted two EOT claims that have not been ...
  A: The Engineer can issue instructions provided that the taking over certificate has not been issued ...
Escalation on Variations2/4/2010liaqat hayat
  Q: 70.1 (Part II Conditions of Contract) says, price adjustment factor to be applied on work done in ...
  A: I have following to say on the points touched in your question. 1)Let me clarify that "C" value ...
Difference between claim under Clause 12.2 and 53.1 (FIDIC 1987 Re 1992).2/4/2010liaqat hayat
  Q: I have a little confusion between these two stated clauses. Both relate to claims. Certainly 12.2 ...
  A: In my opionion,I agree that there is some duplication regarding submission of claims in clause 53.1 ...
ICE Clause 112/4/2010John Dowse
  Q: Order of documents Contract Agreement Schedule of Post Tender Amendments Conditions Employer’s ...
  A: Al, Thank you for the additional information. The situation appears to be far from clear cut. As ...
delay and extension of contract2/4/2010John Dowse
  Q: I am busy on a big project as member of the consultant team. we are using FIDIC 1999 General ...
  A: I am happy that you were satisfied with my earlier response. With regard to the contract being a ...
13.7 Adjustments for Changes in Legislationn2/4/2010Florin NICULESCU
  Q: Is it possible to be taken into account under Sub-Clause 13.7 Adjustments for Changes in ...
  A: Mustafa Bey sellam, Tesekur ederis for your question. That would be next to impossible, first of ...
Engineer's Decision - FIDIC 19872/4/2010Peter M. Elliott
  Q: Is it a prerequisite that the contractor will need to exhaust the contract procedure for claims ...
  A: It is only necessary that a dispute has arisen for the Contractor to ask for an Engineer's Decision ...
construction law2/3/2010Shan Greer
  Q: i got the job of roofing a house, at the time the job came up i was unable to do it so i ...
  A: The issue is not really whether or not you can hold him responsible. If you signed a contract with ...
delay and extension of contract2/3/2010John Dowse
  Q: I am busy on a big project as member of the consultant team. we are using FIDIC 1999 General ...
  A: In answering I assume that the FIDIC conditions have not been amended for the project. I also assume ...
FIDIC interim payments2/3/2010Nasir Gilani Syed
  Q: I am a quantity surveyor on a construction site in the UAE appointed by the client. Every month ...
  A: client cant deduct any monies, except there is a certified employer's claim against contractor. ...
Variation Rates2/3/2010Peter M. Elliott
  Q: We are PQS on a 5 star hotel project. The project contract is Item Rate basis with a Preliminary ...
  A: What is defined as 'cost' in the contract? If there is nothing defined then your definition is as ...
EOT Claim2/3/2010Florin NICULESCU
  Q: I have to clarify followings regarding EOT claim, 01.This contract under FIDIC yellow book,I am ...
  A: 1. Use last phrase of 5th paragraph of Sib-Clause 20.1 and subsequent point a) and b), respectively ...
PAYMENT ON MATERIAL ON SITE2/2/2010Florin NICULESCU
  Q: IF I PAID MATERIAL ON SITE OF R300 000.00 IN PAYMENT CERTIFICATE NO.2, AND WHEN WE MEASURE FOR ...
  A: You should definitely not pay twice for anything. You have paid that amount for the materials and in ...
ICE Clause 112/1/2010John Dowse
  Q: Order of documents Contract Agreement Schedule of Post Tender Amendments Conditions Employer’s ...
  A: Alan, Thank you for your question. I do not have a copy of the ICE General Conditions of Contract ...
MATERIALS ON SITE2/1/2010Peter M. Elliott
  Q: am working in a mep project as qs in our project we calim for materials on site with the copies of ...
  A: How can you claim for materials that have been returned, for whatever reason? If I was the ...
risk register1/31/2010Florin NICULESCU
  Q: am working as a trainee QS in an MEP project can u please help me to understand what is ment by risk ...
  A: Firstly, please note there is no standard format recognised across the industry, it is rather a ...
Approved drawings1/30/2010Nasir Gilani Syed
  Q: I am working in an interior contracting company and we received one of the commented drawings by the ...
  A: Mr. Mohammad, Though I have replied your question before but still it is shown in my account, reply ...
Claim validity1/30/2010Peter M. Elliott
  Q: We are the contarctor working under FIDIC 1987 and are considering to forge ahead with a claim due ...
  A: You might have a chance with delay and disruption if the delay in specifying the tiles affected your ...
advance payment recovery1/30/2010Alina Valentina Oprea
  Q: could u pls explain the methods for recovery of the advance payment in construction contracts in ...
  A: You’re welcome. See below your next answers. From the details you have provided I understand that ...
As built drawing1/30/2010Peter M. Elliott
  Q: If there is no BOQ quantity for as built drawing, and the tender document does not specifically ...
  A: You can claim for the cost, but will the Engineer except it? If there is no mention of the need to ...
Price Adjustment in Fidic 1999 Yellow Book1/29/2010Daniel Kazado
  Q: Could you please inform what you understand from the below sentences of Clause 13.8 in Fidic 1999 ...
  A: 2. Yes Correct. 3. You may request for it with relevant evidences, but it is still subject to ...
advance payment recovery1/29/2010Alina Valentina Oprea
  Q: could u pls explain the methods for recovery of the advance payment in construction contracts in ...
  A: 1. One used method of recovering the advance payment is to start the recovery of the advance payment ...
Price Adjustment in Fidic 1999 Yellow Book1/29/2010Daniel Kazado
  Q: Could you please inform what you understand from the below sentences of Clause 13.8 in Fidic 1999 ...
  A: With reference to your items ; 1. The sentence means that; If this clause 13.8 is applicable in ...
Prolongation Cost1/28/2010Florin NICULESCU
  Q: The Contractor, while submitting his claims for prolongation cost, has shown Bonus to his employees. ...
  A: I am not sure I understand what kind of bonus are you referring to. If it was a bonus the ...
Is a Contractor's proposal a variation - FIDIC 19991/28/2010Peter M. Elliott
  Q: I work for a contractor in the UAE using FIDIC Conditions of Contract for Construction for building ...
  A: I suspect that the Engineer approved your proposal on the basis of no time or cost effect. It is ...
Drafting changes in Drawings constitute a variation?1/28/2010Daniel Kazado
  Q: Our sub-contractor submitted a variation for the changes in the alpolic panels. Originally the ...
  A: If there is an instruction to make a change in the design then the Contractor is entitled to request ...
Excessive Counterclaim1/28/2010Shan Greer
  Q: I was contracted to install a driveway for a client.£32000.A payment schedule was in place that the ...
  A: I have a better understanding of the question but I'm not sure why they are of the view that this is ...
fidic 1987 revised1/27/2010Peter M. Elliott
  Q: What weight does a tender program carries? The contractor is yet to submit his program under clause ...
  A: The tender programme has little weight if it is not defined in the contract documents or in the ...
Surplus Material1/27/2010senthilkumar sellamuthu
  Q: I am a Quantity Surveyor working for Contractor in Qatar. I am just reproducing a clause of General ...
  A: Babu, 1. Can I understand the clause like – the surplus material pertaining to the items which are ...
Arbitration1/27/2010John Dowse
  Q: The Engineer given a decision against contractor according to fidic 87. In the light of the decision ...
  A: I apologise if there has been a delay in responding to you. I have been changing my Internet service ...
Excessive Counterclaim1/26/2010Shan Greer
  Q: I was contracted to install a driveway for a client.£32000.A payment schedule was in place that the ...
  A: I believe that this is unreasonable behaviour. In order to substantiate a claim for the cost of ...

Page:   1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10  |  Next      All


Questions by
Active Experts:
Shan GreerJohn Dowsesenthilkumar sellamuthu
Nasir Gilani SyedAlina Valentina OpreaDaniel Kazado
Florin NICULESCUliaqat hayatPeter M. Elliott
   

Email this page
     
User Agreement | Privacy Policy | Kids' Privacy Policy | Help
Copyright  © 2006 About, Inc. AllExperts, AllExperts.com, and About.com are registered trademarks of About, Inc. All rights reserved.