AllExperts > Experts 
Search      

Construction Law

Volunteer
Answers to thousands of questions
 Home · More Questions · Answer Library  · Encyclopedia ·
More Construction Law Answers
Question Library

Ask a question about Construction Law
Volunteer
Experts of the Month
Expert Login

Awards

About Us
Tell friends
Link to Us
Disclaimer

 
 
 
 
About Daniel Kazado
Expertise
I can answer questions related with FIDIC contracts.

Experience
10 years as Contract Manager for FIDIC contracts.

Education/Credentials
Mechanical Engineer
Contract Management - Basic Principles Certificate. Construction Contracts and Dispute Resolution Certificate. Contract Administration - FIDIC Certificate.
 
   

You are here:  Experts > Industry > Construction Industry > Construction Law > Failure of Nominated Subcontractor to Perform

Topic: Construction Law



Expert: Daniel Kazado
Date: 7/3/2008
Subject: Failure of Nominated Subcontractor to Perform

Question
Dear Daniel,

the question is:-
"Main contractor entered into a contract with the Nominated Subcontractor based on an agreed Clause 8.3 program for the Project.The nominated Subcontract at the mid of the project submits a rediculous revised program which affects the end date and they confirm they cant do anything better that it.Since the work which the Nominated Subcontractor is handling is a specilized design built works therefore appointing new contractor wont solve the purpose neither levying Liquidated damages as the amount of damages which client will levy will be a lot more than what he can't recover from the Nominated Subcontractor.

Now as its a failure on the part of the Nominated Subcontractor, therfore client is equally resposible for his failure. This argument for the Main Contractor can provide them an Extension of Time & money?

Regards,

KP


Answer
Yes the contractor has right to request for EOT and relevant costs from the Employer because of Default of Nominated Sub-contractor. Please check the clause related with default of Nominated sub-contractor. In addition Main contractor shall prove with evidences that they do not have any effect on this delay. In addition main contractor shall not be delayed in other works which are not related with nominated sub-contractor. If the Employer has also signed the contract of the nominated sub-contractor it will add more evidence to the claim file.

Regards

Daniel Kazado

View Follow-Ups    Add to this Answer    Ask a Question



  Rate this Answer
   Was this answer helpful?
Not at allDefinitely              
   12345  

     
About Us | Advertise on This Site | User Agreement | Privacy Policy | Help
Copyright  © 2008 About, Inc. About and About.com are registered trademarks of About, Inc. The About logo is a trademark of About, Inc. All rights reserved.