Construction Law/extention of time - fidic 1999

Advertisement


Question
In a item rate construction contract, employer has already agreed and granted extention of time. Employer contention now is granting extention of time to contractula completion date does not mean that contracual intermidiate mile-stone dates also change. Employer wishes to levy LD for slippage in milestone dates. Our opinion is that once EOT is granted employer can not levy LD. What do you advise.

Answer
Dear Mahim,

We have to see under what heads and for what milestone the extension of time is granted. If there are intermediate milestones, and if the Employer has granted an extension to all of them or has not specified to which specific milestone he is granting an extension, then by default, all the milestones are re-casted and extension applied to all of them.

Regards.

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Ashish Gurav

Expertise

I can answer queries related to Construction Contracts, Claims, Dispute Resolution Mechanisms.

Experience

I have nearly 19 years experience in Construction Contracts, ranging from mega infrastructure projects to residential buildings and commercial complexes. I have worked with major construction companies in India and now I have my own consultancy firm.

Education/Credentials
BE Civil, MMS (Finance), CFA, BGL

©2012 About.com, a part of The New York Times Company. All rights reserved.