Just want to ask if Contractor can prepare variation order request to Subcontractor? Is it right or happen that contractor must be the one to prepare VOR to Subcontractor?

Answer
dear Jack
Variation request are usually prepared by the main contractor for the approval of the Engineer/Employer. it is normal that the subcontractor prepare such request when all of the variation works is related to the subcontractor works. it does not make since for the subcontractor to prepare something outside of his scope of works.
Cheers

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Wael Ghadban

Expertise

Will respond to queries related to Engineering Contracts subject to FIDIC or other Conditions, tendering and contracting, project management, residential and commercial construction, and general Civil Engineering questions. Can answer most questions related to aviation and airports as related to the Airports, Facility management.

Experience

Project construction and Management Civil Aviation - Airports Airport Pavement Design and Use Residential and commercial construction ICAO and FAA regulation

Organizations
-

Publications
-

Education/Credentials
MS Civil Engineering

Awards and Honors
-

Past/Present Clients
-

©2016 About.com. All rights reserved.