Dear S.K. Sellamuthu.
The scenario is like this; We are the Consultants to the one project, the construction period was elapse but the Contractor was grated an EOT which also has expired. The contractor was submit his notification on possible delay one moth before expiration of EOT, after two weeks he submit his application of second (2nd) EOT. In our internal discussion Project Manager advised to issue an Interim Extension of Time mean while the Contractor is preparing the substantiations on the requested time (EOT).
My questions are: i. The Project Manager entitled to grant an Interim Extension of Time?
ii. Is there any Clause which allow an Interim Extension of Time (IEOT) in any form of contract (i.e. FIDIC)

Thanks,
Godfrey M. Mkumbo
Project Quantity Surveyor

Answer
Dear Sir,

Kindly note that FIDIC Civil clause 44.3 Interim Determination of Extension and FIDIC  E&M clause 26 are relevant for your reference.

Under your case, the Project Manager shall wait for the submission of detail particulars for the request by the contractor. Maximum, the Project Manager may acknowledge the intent of claim from the contractor with being attested to the conclusion reached after detail particulars.
Best Regards

Best Regards

Akhtar Hussain Mayo  

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Akhtar Hussain Mayo

Expertise

I am interested to comment on Project planning/scheduling, schedule updating, extension of time delay analysis, concurrent delays, extension of time, extension of time delay compensation cost analysis, up to some extent on contractual matters, for the sake of my learning

Experience

worked on a Eot and cost compensation claim in 1992 for 34 million USD, 1987-1992 worked as RE technical at Tarbela third extension, Pakistan, 1992-1996 scheduling and construction claim processing at Lahore/Karachi on Thermal projects, 1197 to 2006 in Saudi Arabia project scheduling/coordination/monitoring and managing the multiple activities for completing four 300 beds hospitals in different parts of the world, since 2006 to date working for scheduling, delay analysis, cost compensation Eot claims and project monitoring. Also, Quality manuals review, monitoring and quality audit

Organizations
National Engineering Services of Pakistan, Lahore, since 1982 - to date.

Publications
published my method in "The Engineer" Delay cost analysis through as-planned verses as-built and as-adjusted time schedule. 1991

Education/Credentials
1976-81 Bsc Engineering (Mechanical), UET (Lahore) 2007-2009 MS TQM (Total Quality Management) PU (Lahore) courses in CPM/PERT PIM Lahore Project planning/Control work shop ARAMCO, Dahran Primavera users conference in Jeddah. Heat recovery systems quality inspection in China 220 Kv transmission line tower manufacturing quality assurance at Lahore

Awards and Honors
- Best service award from Saudi German Hospitals Group (SGH), Jeddah during the construction planning/scheduling and monitoring of Abha Hospital, Saudi Arabia. - Selected as Steering Committee member for SGH Group, Jeddah. - Selected as Strategic Committee for business development, SGH, Jeddah. - Headed the committee for standardized recrutment of medical staff from different parts of the world for initial start-Up of hospitals.

Past/Present Clients
Water and Power Development Authority KaracHi Electric Supply Corporation Saudi German Hospitals Group,Jeddah Civil Aviation Authority, Islamabad, Pakistan Laraib Energy Limited, Mir Pur Azad-Kashmir, Pakistan Central Power Generation company processing the Eot Claims and cost compensation of claims CPGCL-GENCO-II, Lahore

©2016 About.com. All rights reserved.