Construction Law/fuel indice-variation of price


Dear Sir
we are working in a road project as a consultantin Uganda
we are following FIDIC 1987
our contractor indicated source of fuel as Saudi Arabia
but he is procurring fhel from local marker
is he eleigble for change of source of country.

Dear Bala
if the contractor has gone through the proper process of notifying and filing the said change , then he would be eligible provided that the use of different source has imposed additional charges  on the contractor and that is nor part of the contract. Please note that all contractual changes has to be approved by the Employer.

Construction Law

All Answers

Answers by Expert:

Ask Experts


Wael Ghadban


Will respond to queries related to Engineering Contracts subject to FIDIC or other Conditions, tendering and contracting, project management, residential and commercial construction, and general Civil Engineering questions. Can answer most questions related to aviation and airports as related to the Airports, Facility management.


Project construction and Management Civil Aviation - Airports Airport Pavement Design and Use Residential and commercial construction ICAO and FAA regulation



MS Civil Engineering

Awards and Honors

Past/Present Clients

©2016 All rights reserved.