Question
Dear Manish,

In general it is possible to hold payment for preliminaries (time related) if Contractor's progress is very slow or far behind the program.

Thanks & regards

Tharindu

Answer
Dear Tharindu,

Please let me know which form of contract exists between the parties.

However, in general the prelims ,the ones referring to time related expenses can be reduces if the Engineer finds out that the progress is slow and resources deployed are below baseline histograms.

Thanks

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Manish Gupta

Expertise

I can answer questions related to Cost Planning, Contract Administration, Construction Law & Other Post Contract QS related areas.

Experience

7 Years with Contractors 12 plus Years with Owners & Consultants

Organizations
Calgary Project Consultants, Jacobs International, Turner International, J Ray McDermott Inc. Hindustan Construction Company

Education/Credentials
MRICS, MCIArb, BE (Civil), PGDCM LLM-Constuction Law in Arbitration and Adjudication

©2016 About.com. All rights reserved.