Construction Law/clarity


dear Alina
using FIDIC 99 yellow book, the Engineer has issued an addendum which is not clear but it could be explained and interpolated in different meaning. Is the contractor correct in refusing to execute the extra works included in the addendum based on ( why the engineer was not very clear on his requirement )
Please advise

Hi, Wael,
If by "addendum" you really mean an addendum to the Contract, signed by both Parties, then the Contractor cannot refuse to execute it, since he agreed on it when signing it. The Contractor can ask clarifications on the issues within the addendum and after can try to demonstrate that a reasonable meaning should be considered.
If you refer to an instruction or a Variation (not agreed and signed in either way by the Contractor), the Contractor can ask clarifications, and, if the Contractor cannot execute the instruction or variation, the Engineer can vary the variation or instruction, as per the Sub-Clause 13.1.
Hope ir helps.
Best regards,

Construction Law

All Answers

Answers by Expert:

Ask Experts


Alina Valentina Oprea


I can answer to questions regarding FIDIC 1999 contracts, including practical use of these conditions of contract, as well as to questions regarding dispute boards, both from theoretical and practical point of view. I cannot answer to questions related to other kind of contracts or to procurement process, except to some (limited) extent.


Implementation of works contracts (FIDIC 1999) financed by different financial institutions, including European Union; claims and disputes; dispute boards See more on

Dispute Resolution Board Foundation

see ; DRBF Forum Newsletter; Drumuri si Poduri; Revista Constructiilor; SIDiR Newsletter

Graduated the University of Civil Engineering Bucharest, Faculty of Railways, Roads and Bridges (1985-1990); Trained under Mr. Gwyn Owen’s pupilage program for arbitrators/adjudicators under FIDIC mentoring program (2006 – 2007)

©2016 All rights reserved.