Under FIDIC GCC Cl14. If an IPC is issued late you are entitled to financial charges without notice or certification. This is calculated at whatever the interest rate is at the country you are in bank plus 1%.

Under GCC Cl 16 you are entitled to give a 21 day notice to the Eng and suspend works or reduce the rate of work drastically. Until the Eng pays the IPC(s) or notification is givenm. If not approach the DAB and tell them the situation. If still no resolution you are the entitle dto go to arbitration.  

Construction Law

All Answers

Answers by Expert:

Ask Experts




Questions related to Civil Engineering Contracts, using FIDIC or other Conditions of Contract, concerning Procurement procedures and documents (pre-qualification, tendering and contracting) and Services/ Works Contracts implementation matters including Determinations, Payments, Time Extensions, VOs, Claims/Disputes. Additionally, questions related to dealing with International Financing Institutions. Can also answer questions in Romanian. Can not answer improperly formulated questions.


Over 20 years of experience in the field of design, works supervision, construction, management of aid funds and technical assistance for various types of contracts implementation, including severe conflictual contractual situations leading to Claims and disputes. Claims/ Contract management, Disputes adjudication, Arbitration.

Member of Romanian Professional Association of Roads and Bridges; Listed on President's List of Adjudicators of Romanian Association of Consulting Engineers Former member of the Disputes Resolution Board Foundation (DRBF) of United States – nominee on DRBF President’s Disputes Board Members List and of DRBF Chapter for Eastern Europe Former member of Polish Association of Consulting Engineers (SIDiR) – nominee on SIDiR President’s Disputes Board Members National List Member of “” volunteers pool Member of the "Constructions Disputes Resolution Services” International Panel of Construction ADR Specialists" of United States

- Graduate in 1994 the Construction Institute - Graduate of several FIDIC,Procurement and other courses - Graduate of first Disputes Board Members Mentoring Scheme ( - FIDIC Accredited Adjudicator

Past/Present Clients
- Several State organisations/Ministries , such as Ministry of Transport, National Admistration of Roads, Ministry of Regional Development (former Ministry of European Integration), Public Works and Housing, Central Contracting and Financing Unit in Romania and also in Turkey, Croatia and Macedonia - Numerous Western based private consultancy companies - full CV and other relevant information available at

©2016 All rights reserved.