Question
hi, during tender we apply a discount rate for the total sum of the whole B.O.Q item's my question is this discount  apply  for the additional quantity or  only B.O.Q quantity;  consultant insist to apply the discount for the additional quantity

Answer
Dear Anwar
Thank you for this question.
the discount you offered has set a new price for the for the BOQ items. When additional work is ordered, the new price will obviously be used to calculate such variation . We need to remember that the BOQ main purpose is to detail the price breakdown for the use of payment and calculation of + or - variations.
CHEERS

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Wael Ghadban

Expertise

Will respond to queries related to Engineering Contracts subject to FIDIC or other Conditions, tendering and contracting, project management, residential and commercial construction, and general Civil Engineering questions. Can answer most questions related to aviation and airports as related to the Airports, Facility management.

Experience

Project construction and Management Civil Aviation - Airports Airport Pavement Design and Use Residential and commercial construction ICAO and FAA regulation

Organizations
-

Publications
-

Education/Credentials
MS Civil Engineering

Awards and Honors
-

Past/Present Clients
-

©2016 About.com. All rights reserved.