You are here:

Construction Law/Fidic red book 1999 and harmonised edition 2010

Advertisement


Question
Dear mr. Mahmoud,
Please can i know the difference between tge fidic red book 1999 and the harmonised MDB 2010?
Thank you in advance .

Answer
Dear Mr.Rash,

Red Book 1999 is a standard book prepared by FIDiC whereas MDB Hormonized 2010 is its revised Eddition based on the conditions of Red Book 1999 with some minor changes,being used on various Projects of ADB, World Bank and JICA etc.For example, In Red Book ,under Sub-clause3.5,there is notime specfied for the Engineer's determination whereas in IN 2010,there is a time frame of 28 daysfor the Engineer's determination.Similarly, in Red Book,there is DAB for dispute resolution whereas in MDB Hormonized 2010, there is DB for this purpose.We may say that Contracto'r rights are more protected in MDB Hormonised Version. Hope I have the answered.
Regards
Engr. Arshad Mahmood

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Arshad Mahmood

Expertise

I may answer to the questions relating to FIDIC 4th as well as FIDIC 2010 MDB Harmonized version,price adjustment ,Variations,Eot and Cost claims,EPC Contract,Bidding Document,consultancy Contracts,certification,Standard Forms, Dispute resolution; and others pertaining to Contract implementation.

Experience

Contract management and Contract Administration, using FIDIC Conditions of 4th Addition as well as Fidic 1999 Red, Yellow and Silver Books including MDB Harmonized Edition 2010. Particularly in the area of Procurement of Contracts, Certification,Price Adjustment, variations,disputes management, EoT and Cost Claims; and other contractual issues arises from time to time during currecy of the Contracts.

Organizations
Member -Pakistan Engineering Council Member -Pakistan Engineering Congress Member -FIDIC Organisation

Publications
Joint Venture and Consortium Agreements for Pakistan Engineering Council,Pakistan

Education/Credentials
BSc Civil Engineering; Basic Management course; Hydro power Projects; and various other on Job Trainings

Awards and Honors
Commendation Certificate for the excellent management qualities and dedication at Ghazi Barotha Hydropower Project; and Certificate of Excellent work performed during Survey Camp.

Past/Present Clients
Water and Power Development Authority (WAPDA),Associate Consulting Engineer(ACE) and National Engineering services Pakistan(Pvt.) Limited (NESPAK)

©2016 About.com. All rights reserved.