Do all site instructions constitute variation orders?

Answer
Mr Louis,
All the instructions need not necessarily a variation. But an instruction may result in a variation. the variation may be increase or decrease in cost, time, scope or the combination of these three aspects.
Following an instruction, the contractor has to notify the Engineer or owner if the instruction results in variation if any with back and justification.
--r sivaraman

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


R.Sivaraman

Expertise

I can answer the questions related to Engineering design, Project management and contract management

Experience

I have 20 years of experience across a wide spectrum of engineering and project management knowledge areas

Organizations
Member in the Institution of Engineers Member in the Institution of technical arbitrators

Education/Credentials
Bachelors in Civil Engineering Masters in Business Administration

Past/Present Clients
Capgemini Johnson & Johnson EMC FM Global SABIC

©2016 About.com. All rights reserved.