Construction Law/Extended Stay Cost


I wanted to know whether Extended Stay Costs is applicable during FORCE MAJEURE PERIOD in Item Rate/Unit rate Contract.

dear Sir
pending to what is written in your Contract
In FIDIC Contracts this aspect is clearly stated under Clause 19
therefore in some cases of Force Majeure the Contractor is entitled to extension of time and in some cases to an extension of time and costs.
From you question it is not clear in which circumstances we have a force majeure event
Best regards