Construction Law/Schedule of rates


Dear Sir,

Our Contract is a Measure and pay Contract(Method of measurement SMM7) and based on FIDIC 1987.

This is a hotel project.Schedule of rate has been given for swimming pool work deleted the BOQ items related to that work.At the Construction stage details were changed.Therefore Construction of swimming pool has to be claimed as a variation to the Contract.

Do we need to use Schedule of rates for pricing of variation proposal or else possible to use new rates?

An early reply is very much appreciated.
Thank you..

Sub-clause 52.1 is relevant.

Applicable rates mentioned in the Contract shall be used for varied items.

If no rates is applicable, new rates shall be allowed but shall still be based on existing rates mentioned in the contract which shall be reasonable.


Jonathan Peralta

Construction Law

All Answers

Answers by Expert:

Ask Experts


Jonathan L. Peralta


Questions relating to claims, Extension of Time, Variations, Interim Payment and delays utilizing FIDIC Form of Contracts.


Extensive experience gained from international contractors in Vietnam, Myanmar and the Philippines in various sectors including: infrastructures, marine works, civil and buildings.

AACEI, U.S.A., Dispute Resolution Board Foundation,U.S.A., ASCE, U.S.A., PICE,Philippines

Bachelor of Science in Civil Engineering, Registered Civil Engineer in the Philippines

©2016 All rights reserved.