Construction Law/Delayed payment


Please draw your attention to the following situation related to delayed payment for performed works and share your opinion.
1. Contractor is delaying payment for the works performed by, us, ie. subcontractor referring to the fact that the supporting documents should be revised, although the engineer approved IPA s conditionally and issued IPCs.
2. According to the subcontract (not FIDIC contract), which is one sided contract favoring the contractor, cl. 7.12 "the subcontractor shall be paid within 5 days after the contractor receives payment otherwise the the subcontractor reserves right to stop performing works and after 28 days the subcontractor may refer the issue to ADB".
3. However the contractor ignoring this clause provision and not paying us.
So instead of it can we apply FIDIC contract clauses executed between the contractor and the employer, eg.14.3 Application for IPC, 14.8 Delayed payment and claim financing charges as stated therein.
I would be happy if you could give some advice.

Dear Adsil
I am trying to reply your question.
First of all, If you are appointed as the subcontractor with due permission of Engineer or you are nominated subcontractor then you are liable to raise the issue to the Engineer.Engineer can advise to client to insist to the contractor to clear the dues,otherwise client may pay the amount and can be deducted from the contractors payment.
Secondly, if you are not appointed as subcontractor then you are liable to raise the issue to the
Engineer. Then Engineer may take the action against the contractor.

I hope you will get the directions.
With due regards

Construction Law

All Answers

Answers by Expert:

Ask Experts


Sanjay Khandelwal


I can answer related to the various construction contracts forms related with disputes and claims.Expertise in to evalute the extension of time,cost and profit claims.I can answer regarding the contract management in civil works.


I have the experience of construction industry, as a consultants,executor of construction activities of infrastructure development like road and buildings. I have the experience of various software related to design of highways and quantity evaluation.

I am life member of Indian Road Congress,INDIA I am presently employed with M/s Lion Engineering Consultants,INDIA

My educational qualifications are as below: I am engineering graduate from MITS, INDIA,1987 I have completed my Post graduation from NIT,INDIA,2011

©2016 All rights reserved.