Question
Dear Femi,
Greetings!
I have a question Oh/ P for a new item. As per original contract, the contractor's OH/P profit was 6%. However, a new item was introduced recently and the contractor request 15% Oh/P for the new item. Is the contractor entitled for 15% when the contract says 6%?
Rgds,
Priyan

Answer
Dear Priyan,

Thanks for your question.

From you narration, the Contract is very clear on what percentage to apply and therefore, what Contractor is asking for is obviously not contractual and as such, could be rejected and you can refer the Contractor to the relevant provision where the 6% is stated instead of the 15% he is asking for. None of the parties has power to unilaterally change the Contract without the other parties' consent.

Thanks.

Femi

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Femi Alofe

Expertise

I can answer all questions relating to the followings: 1. Contract Administration - variations, contract clauses interpretation, all post contract procedures, valuations and certificates questions, extension of time issues and prolongation cost matters. 2. Contract Practice - Any questions regarding forms of contract like JCT, FIDIC & other Bespoke forms. 3. Quantification, measurements and Estimating questions 4. Contracts and construction law questions and dispute resolutions problems. 5. All FIDIC Conditions of contracts

Experience

Out of my 24 years experience in construction industry, i have the following specific experience: 1. Contract Administration - 15 years in contract administration with over 10yrs in Managerial positions covering africa and the middleeast. 2. Contract Practice - 15 years experience with over 10yrs in Managerial and expert positions covering africa, north america and the middleeast. 3. All pre-contract procedures, Tendering, Quantification, measurements and Estimating questions - 20 years experience. 4. Contracts and construction law questions and dispute resolutions problems - 15 years experience with over 10yrs in Managerial and expert positions and 5 years expert witness and active practice in arbitration proceedings covering africa and the middleeast.

Organizations
1. FAIQS - Fellow, Australian Institute of Quantity Surveyors, Australia 2. FRICS - Fellow, Royal Institution of Chartered Surveyors, UK 3. CCP - Certified Cost Professional AACEI, USA 4. PQS - CIQS, CANADA 5. ACIArb. - CIArb, UK 6. MNIQS - NIQS, NIGERIA 7. RQS - QSRBN, NIGERIA

Publications
1. AACEI RP on Estimating, 2010

Education/Credentials
1. B.Tech (QS) 2. RICS professional course, CEM - UK 3. MSc , UK NARIC 4. Professional Doctorate ( to commence 2016)

Past/Present Clients
1. Larsen & Toubro Ltd, Dubai UAE 2. Larsen & Toubro (oman) LLC 3. Archi + Web consortium, Abuja Nigeria 4. George Dike & Associates, Minna Nigeria 5. Public works Authority (Ashghal), Doha Qatar

©2016 About.com. All rights reserved.