G.S.Rao wrote at 2014-05-14 11:05:05
The factor 0.85 P means only 85% of value of work done is considered for escalation purpose. The balance 15% is fixed component of work done which is not considered for escalation.


Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Sanjay Khandelwal

Expertise

I can answer related to the various construction contracts forms related with disputes and claims.Expertise in to evalute the extension of time,cost and profit claims.I can answer regarding the contract management in civil works.

Experience

I have the experience of construction industry, as a consultants,executor of construction activities of infrastructure development like road and buildings. I have the experience of various software related to design of highways and quantity evaluation.

Organizations
I am life member of Indian Road Congress,INDIA I am presently employed with M/s Lion Engineering Consultants,INDIA

Education/Credentials
My educational qualifications are as below: I am engineering graduate from MITS, INDIA,1987 I have completed my Post graduation from NIT,INDIA,2011

©2016 About.com. All rights reserved.