Question
Hi,

In our BOQ there are it is specifically mentioned some measurable items, my question is can I change the BOQ quantity thus changing also the BOQ price when I submit the monthly application?

Answer
Dear Aries,

This really depend on what form of contract you are using, type of contract and some provisions included in your contract which relates to variations, valuation, payment and measurement.

You may need to check your contract for this provisions and look if something is written. I am afraid I cannot give further details due to limited information.

Regards,

Jonathan L. Peralta

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Jonathan L. Peralta

Expertise

Questions relating to construction claims, Extension of Time, Variations, Interim Payment and delay analysis under FIDIC Form of Contracts.

Experience

Experience in the following sectors: buildings, residential, infrastructure, civil and marine works. Have worked for different international contractors in Myanmar, Vietnam and the Philippines.

Organizations
AACEI, U.S.A., Dispute Resolution Board Foundation,U.S.A., ASCE, U.S.A., PICE,Philippines

Education/Credentials
Bachelor of Science in Civil Engineering, Registered Civil Engineer in the Philippines

©2016 About.com. All rights reserved.