Construction Law/Contract Agreement


Dear Expert,

In one of our Contract which is based on FIDIC MDB 2010 Conditions of Contract, a Variation(amendment) to the Contract Agreement was signed between the Parties  during the currency of the Contract wherein simply the Accepted Contract Amount was amended(reduced) without stating any reasons or repercussions of the this Variation. We, being the Engineer, have used this revised Accepted Contract Amount in order to deduct Advance Payment from Contractor’s Payment Invoices. But the Contractor did not agree with the Engineer’s stance by stating that Accepted Contract Amount means the amount accepted in the letter of Acceptance as per Contract. But the Engineer’s is of the view that Variation (amendment) of Contract Agreement has priority over all Contract Documents, therefore this revised Accepted Contract Amount will prevail as per amendment.

Please advise in this regard.


Umer Shabbir

Dear Umer,

Thank you for your questions.

As defined under Sub-Clause “Accepted Contract Amount” means the amount accepted in the Letter of Acceptance for the execution and completion of the Works and the remedying of any defects.

Hence, that can not be modified, it is the price at the time of accepting the tender.

Of course, that price will most likely and will result, as defined under Sub-Clause, the “Contract Price”, which means the price defined in Sub-Clause 14.1 [The
Contract Price ], and includes adjustments in accordance with the Contract.

As such, you have a VO that in my opinion is wrong. It should be have been modified the Contract Price, of course, with indicating reasons. Price can not change alone, there should be revised all other advance/ retention/ payment/ insurances mechanisms and as the case may be, quantities of certain works.

Trust that clarifies the matter.

Construction Law

All Answers

Answers by Expert:

Ask Experts




Questions related to Civil Engineering Contracts, using FIDIC or other Conditions of Contract, concerning Procurement procedures and documents (pre-qualification, tendering and contracting) and Services/ Works Contracts implementation matters including Determinations, Payments, Time Extensions, VOs, Claims/Disputes. Additionally, questions related to dealing with International Financing Institutions. Can also answer questions in Romanian. Can not answer improperly formulated questions.


Over 20 years of experience in the field of design, works supervision, construction, management of aid funds and technical assistance for various types of contracts implementation, including severe conflictual contractual situations leading to Claims and disputes. Claims/ Contract management, Disputes adjudication, Arbitration.

Member of Romanian Professional Association of Roads and Bridges; Listed on President's List of Adjudicators of Romanian Association of Consulting Engineers Former member of the Disputes Resolution Board Foundation (DRBF) of United States – nominee on DRBF President’s Disputes Board Members List and of DRBF Chapter for Eastern Europe Former member of Polish Association of Consulting Engineers (SIDiR) – nominee on SIDiR President’s Disputes Board Members National List Member of “” volunteers pool Member of the "Constructions Disputes Resolution Services” International Panel of Construction ADR Specialists" of United States

- Graduate in 1994 the Construction Institute - Graduate of several FIDIC,Procurement and other courses - Graduate of first Disputes Board Members Mentoring Scheme ( - FIDIC Accredited Adjudicator

Past/Present Clients
- Several State organisations/Ministries , such as Ministry of Transport, National Admistration of Roads, Ministry of Regional Development (former Ministry of European Integration), Public Works and Housing, Central Contracting and Financing Unit in Romania and also in Turkey, Croatia and Macedonia - Numerous Western based private consultancy companies - full CV and other relevant information available at

©2016 All rights reserved.