You are here:

Construction Law/Prolongation Costs in case of Concurrent Delay

Advertisement


G.V. Seshaiah wrote at 2015-11-20 10:37:13
I could probably chip in with my views as below:

For the 7 months of concurrent contractor's delays, the value of works carried out by the contractor may be computed under (1) contractor's own delays and (2) the EOT caused works separately and a proportionate payment of overheads could be recommended for the EOT caused works.  


Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Liaqat Hayat

Expertise

I can answer questions based on FIDIC 4 and FIDIC 1999 [design-build] with particular reference to time extension , price adjustment and disputes. I am in particular more inclined for response to points pertaining to how claims should be framed and put up in case of technical or other contractual shortcomings. Regarding procurement matters I have spent over 5 years as procurement specialist for highway authority and dealt with numerous claims and disputes in the capacity of "The Engineer" .

©2016 About.com. All rights reserved.