Construction Law/EOT due to rain

Advertisement


Question
QUESTION: Dear Peter,
Recently, though the consultant believes the Contractor can work with the current climatic condition, the Contractor is claiming he was unable to work due to rainfall ranging from 1mm to 30mm. Is there any figure that i can consider as a minimum number? I remember in few project as 7mm. To add more, the Contractor in his program he planned for working hours of 5 hours out of the normal 8 hours.
Kind regards,

ANSWER: Dear Aman,

You do not mention the form of contract nor the applicable law, so the following comments will be general in nature.  

I do not know of any minimum value for rainfall to affect progress.  Most contracts talk about adverse weather, which it is generally considered to mean worse than the average of the past ten years.  It would seem that in your case, the Contractor would have to prove his delays by detailed records of the stoppage for each day and each section of the works, and that he could not work the programmed 5 hours per day.  .  

---------- FOLLOW-UP ----------

QUESTION: Dear Peter,
I thank you so much for your response. To give more information, our project is a road project of Harmonized Fidic 2005. By the way in our contract it does not clarify if it should be worse than the average of the past ten years.
Kind regards,

Answer
Dear Aman,

Clause 8.4 (c) exceptionally adverse climatic conditions is relevant.  How to define 'exceptionally adverse climatic conditions'?  Generally it is accepted that the climatic conditions are worse than the average of the past 10 years, based on the premise that the Contractor will have allowed for normal climatic conditions when pricing his offer.  If the Contractor wishes to present an alternative standard, then he must provide the necessary evidence, including case law.  

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Peter M. Elliott

Expertise

First response to queries regarding extensions of time, variations orders, site instructions and payment using FIDIC and other forms of Conditions of Contract, based on English Law, and derivatives only. Anyone who needs advice about EoT should download and study the SCL Delay & Disruption Protocol www.eotprotocol.com before submitting a question.

Experience

Value . . .
It's unwise to pay too much, but it's unwise to pay too little. When you pay too much you lose a little money, that is all. When you pay too little, you sometimes lose everything, because the thing you bought was incapable of doing the thing you bought it to do.
The common law of business balance prohibits paying a little and getting a lot. It can't be done. If you deal with the lowest bidder, it's well to add something for the risk you run.
And if you do that, you will have enough to pay for something better.
. . . John Ruskin (1819 - 1900)
"We are too poor to buy something cheap"
.Romanian Proverb 2002
A lean compromise is better than a fat lawsuit. George Herbert (English poet 1593-1633)
I said it in Hebrew, I said it in Dutch,
I said it in German and Greek:
But I wholly forgot (and it vexes me much)
That English is what you speak!" Hunting of the Snark - Lewis Caroll
Match your presentation to the reader!
The joy of food lasts but an hour, of sleep but a day, of a woman, but a month, but the joy of a building lasts a lifetime. Syrian proverb.
Comments and observations leading to improvements in the translation of FIDIC Red & Yellow books into Romanian prior to approval by FIDIC (reference 'Preface to the Romanian edition')

Organizations
Institution of Civil Engineers, Association of Chartered and Certified Accountants, Society of Construction Law, Dispute Resolution Board Foundation

Education/Credentials
B Sc(Hons) in Civil Engineering

©2016 About.com. All rights reserved.