Can the Fixed Non Adjustment Index for Price Adjustment of A Mechanical Project and Civil Project be same. If a Mechanical Project involves procurement of Mechanical Plant as major cost item and its rate has been taken from the supplier's Quotation which will remain valid during the project duration. The Fixed Non-Adjustable index shouldn't be more ? May be around 0.8 (80%)?

Abdul Waheed

Answer
Dear Abdul Waheed,

Indexes in price adjustment formula represents different inputs of a Project, such as Labor, Fuel, Steel, etc. and in accordance with the requirements of project, it is established by the Employer/Engineer during tender documentation. The fixed portion of the formula represents non-adjustable portion such as; Contractor's overhead, site general expenses, profit, etc. Therefore, the fixed portion may be between 15 to 35 % of the total depends on nature of a project and Employer requirements. Regarding your issue based on supplier's quotation, which will remain valid during course of project will not bring any increase to price adjustment formula in case the same used as index. However, getting a supplier's quotation which the price will be fixed during course of project is success of the Contractor regardless of price fluctuations in the market and he may still get increase on same if the index representing material increases.

Best Regards

IRVALI

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


ALI IRVALI

Expertise

FIDIC, Arbitration Procedures, Claim Management, Project Management.

Experience

I have experience of working at 6 countries in MENA region (algeria, Libya, Saudi Arabia, Oman, Pakistan)as the Regional Director and General Manager of a construction company. I have experience on various applications of FIDIC and construction law, arbitration procedures, claim management, project management.

Organizations
CEO of TURCON Construction presently. www.turcon.com.pk

Education/Credentials
M.S. Civil Engineer, Various Courses on Project Management, Seminars on FIDIC.

Past/Present Clients
National Highway Authorities of various countries, Water and Power Development Authorities, Karachi Port Trust, etc.

©2016 About.com. All rights reserved.