Hi,

Our contarct is Lumpsum under FIDIC 99. In terms of Material On site payment, are we entitled to get paid for the quantities required for the project or limited to BOQ.

Regards,

Ragesh

Answer
Dear Ragesh

Thanks for your question.

Since your Contract is Lump Sum , MOS shall be payable based on the quantities required as per Drawings and specifications. However the amount will be limited to the one written in BoQ against that item.

In case of Variations due to design change etc, MOS may be payable on that particular additional amount.

Best regards

Manish Gupta

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Manish Gupta

Expertise

I can answer questions related to Cost Planning, Contract Administration, Construction Law & Other Post Contract QS related areas.

Experience

7 Years with Contractors 12 plus Years with Owners & Consultants

Organizations
Calgary Project Consultants, Jacobs International, Turner International, J Ray McDermott Inc. Hindustan Construction Company

Education/Credentials
MRICS, MCIArb, BE (Civil), PGDCM LLM-Constuction Law in Arbitration and Adjudication

©2016 About.com. All rights reserved.