Construction Law/LS Contract

Advertisement


Question
Dear Sir

If 1999 FIDIC Red Book will be used for the Lump Sum Contract, then what clauses we have to delete/amend & how the substituted/amended clauses shall be appeared.


Br

Sudantha

Answer
Dear Sudantha

The clauses pertaining to Remeasurement shall be amended. Also the Priority of Documents shall be sorted in appropriate manner.

In the Instructions to Tenderers ; lump sum approach should clearly stipulated.

Best Regards

Manish Gupta

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Manish Gupta

Expertise

I can answer questions related to Cost Planning, Contract Administration, Construction Law & Other Post Contract QS related areas.

Experience

7 Years with Contractors 12 plus Years with Owners & Consultants

Organizations
Calgary Project Consultants, Jacobs International, Turner International, J Ray McDermott Inc. Hindustan Construction Company

Education/Credentials
MRICS, MCIArb, BE (Civil), PGDCM LLM-Constuction Law in Arbitration and Adjudication

©2016 About.com. All rights reserved.