You are here:

Construction Law/Re measurement/Lumpsum

Advertisement


Question
QUESTION: Dear Sir

(a)   FIDIC 1999 Red Book - remeasurement

Assume that the drawing shows to install 150L water heater. Due to an error in the BOQ, it is described as 100L. Then the contractor has to use either 150L or 100L water heater rate.


In RE-MEASURABLE CONTRACT if the drawing is priority, then the client's QS can say that although the BOQ is described as 100L water heater, contractor's rate is for the 150L water heater due to priority of document??

or

He can accept that rate is for the 100L water heater in line with BOQ description  and revised rate to be agreed for the 150L water heater as per the drawing which was installed.

Could you clarify what is the correct from the above with reason.

If the contract is lump sum under FIDIC 1999 Red Book what is the correct decision from the above?


(b) 1999 FIDIC Red Book

Sub-Clauses 17.3, (a) to (d) and 19.1, (i) to (iv) are seem to be similar.

Could you explain the application differences of these Sub-Clauses with examples.

Br

Sudantha

ANSWER: Dear Sudantha
In RE-MEASURABLE CONTRACT you get paid for what you do. So if you install a 150 l heater you get paid for that rate. But if your BOQ has only one rate for a 100 l water heater, then you are required to install 150 l as required by drawing, then you should do that and claim for the price difference.

SCL 19.1 defines what is considered a Force Majeure under the contract and scl 17.3 defines what are the risks of the Employer. So a war is considered a force majeure and it is an Employer risk
Cheers

---------- FOLLOW-UP ----------

QUESTION: Dear Sir

In the last paragraph under war condition, what SCL the contractor has to use either SCL 19.1 or 17.3, because the both SCLs stipulate the Contractor's entitlement.

Br

Sudantha

Answer
Dear Sudatha
17.3 is the SCL that identifies what are the risks associated with the Employer. You need to use this scl when claiming. Ie your case should be identified with such risks.
SCL 19.1 is the definition of the force majeure events. you might need to refer to this clause.
Cheers

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Wael Ghadban

Expertise

Will respond to queries related to Engineering Contracts subject to FIDIC or other Conditions, tendering and contracting, project management, residential and commercial construction, and general Civil Engineering questions. Can answer most questions related to aviation and airports as related to the Airports, Facility management.

Experience

Project construction and Management Civil Aviation - Airports Airport Pavement Design and Use Residential and commercial construction ICAO and FAA regulation

Organizations
-

Publications
-

Education/Credentials
MS Civil Engineering

Awards and Honors
-

Past/Present Clients
-

©2016 About.com. All rights reserved.