Construction Law/Valuation of PS

Advertisement


Question
Dear Sir

According to the FIDIC 1999 Red Book, SCL 13.5 (b), the Contractor shall insert his percentage for adjustment of PS in Appendix to Tender.

However in the BOQ also has a provision to insert his attendance fee and OH&P, based on PS amount.

Therefore during the post contract stage, what method the PQS has to pay to the Contractor, either in accordance with Appendix to Tender or BOQ.

Sudantha

Answer
Dear Sudantha,

I extremely sorry for late answering.In fact,it was ignored/mishandled in bundle of emails received.
Anyhow ,here is answer of your Q.

As per my understanding,It should be dealt as per %age mentioned in Appendix to Tender, as under sub-clause 1.5 [Priority of Documents], General conditions have the priority over Schedules.
Regards

Engr.Arshad Mahmood  

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Arshad Mahmood

Expertise

I may answer to the questions relating to FIDIC 4th as well as FIDIC 2010 MDB Harmonized version,price adjustment ,Variations,Eot and Cost claims,EPC Contract,Bidding Document,consultancy Contracts,certification,Standard Forms, Dispute resolution; and others pertaining to Contract implementation.

Experience

Contract management and Contract Administration, using FIDIC Conditions of 4th Addition as well as Fidic 1999 Red, Yellow and Silver Books including MDB Harmonized Edition 2010. Particularly in the area of Procurement of Contracts, Certification,Price Adjustment, variations,disputes management, EoT and Cost Claims; and other contractual issues arises from time to time during currecy of the Contracts.

Organizations
Member -Pakistan Engineering Council Member -Pakistan Engineering Congress Member -FIDIC Organisation

Publications
Joint Venture and Consortium Agreements for Pakistan Engineering Council,Pakistan

Education/Credentials
BSc Civil Engineering; Basic Management course; Hydro power Projects; and various other on Job Trainings

Awards and Honors
Commendation Certificate for the excellent management qualities and dedication at Ghazi Barotha Hydropower Project; and Certificate of Excellent work performed during Survey Camp.

Past/Present Clients
Water and Power Development Authority (WAPDA),Associate Consulting Engineer(ACE) and National Engineering services Pakistan(Pvt.) Limited (NESPAK)

©2016 About.com. All rights reserved.