Construction Law/variation and claim


Nafez shamia wrote at 2015-09-28 08:26:01
the variation comes from client based on his needs to add a new items, modify a contract items, or to change in a particular item scope or limitations. claims initiated from the contractor against the client fault as delay of issuing instructions, delay of approval of drawings, delay in appointing representative to receive and approve executed works, deletion of contracted items affected the estimated items cost, invasion, incursion or interuption of works negatively impacted the contractor schedule.  

Construction Law

All Answers

Answers by Expert:

Ask Experts


Daniel Kazado


I can answer questions related with FIDIC contracts.


10 years as Contract Manager for FIDIC contracts.

Mechanical Engineer
Contract Management - Basic Principles Certificate. Construction Contracts and Dispute Resolution Certificate. Contract Administration - FIDIC Certificate.

©2016 All rights reserved.