You are here:

Construction Law/Questions

SubjectDate AskedExpert
Reducing the supply scope1/31/2012Florin NICULESCU
  Q: Touching base with you after a long time. I still recollect the help extended last time around. ...
  A: Indeed, did not hear from you since long, good to hear again! Glad I could help then. Firstly, what ...
Deductions.1/27/2012Senthil Kumar Sellamuthu
  Q: We are into a Railway Project governed by FIDIC Red bbok 1987.My question is: Can any deductions by ...
  A: Prashant, Thanks for your Questions. Check with your contracts, if its applicable for the Retention ...
Deductions.1/27/2012Ashish Gurav
  Q: We are into a Railway Project governed by FIDIC Red bbok 1987.My question is: Can any deductions by ...
  A: As per Fidic, you have to understand that all interim monthly payments are merely adhoc payments and ...
Programe of works1/27/2012Wael Ghadban
  Q: Can the Engineer enforce the submitted program of works
  A: The engineer should use the contractor's program of work to monitor progress, monitor resources ...
Additional Claims for Variation1/25/2012Senthil Kumar Sellamuthu
  Q: Is site diary and inspection reports confirmed by Engineer's substantial basis for additional claims ...
  A: EDZ, Thanks for your Questions. Yes, You are right. The Site Diary, Inspection Report, ...
Fixed Sum in BOQ1/24/2012ALI IRVALI
  Q: What is the explanation of fixed sum in the Bill of Quantities? I have Contract conditions clause ...
  A: I presume that you are working with FIDIC IV which original text revised directly or through your ...
Contractor to bear travel costs1/24/2012Florin NICULESCU
  Q: Where is it usually stated in contracts where the Contractor is responsible for the cost of the ...
  A: I am in the office, if needed, I can try searching more during the evening, but since you have that ...
Contractor to bear travel costs1/24/2012Florin NICULESCU
  Q: Where is it usually stated in contracts where the Contractor is responsible for the cost of the ...
  A: glad to hear again from you. Right now I am in hurry to the office, so can not search for you, but ...
Rate Enhancement1/22/2012Peter M. Elliott
  Q: A Contractor made an unforeseen physical conditions claim under an Infrastructural Works Contract ...
  A: It is always the political, or personal, rather than technical, effects which make construction so ...
FIDIC 1999 Red book clause 19.6 (b) - Dubai1/22/2012Peter M. Elliott
  Q: In the event of a termination [for convenience] the Contractor is entitled to payment under Clause ...
  A: In this situation, it depends on the costs of the Contractor. If he has to pay cancellation ...
DAB Decision1/19/2012ALI IRVALI
  Q: We are contracted to use FIDIC MDB 2006 version. My question in relation to Sub Clause 20.4-Obtaning ...
  A: A DAB seems to be a quasi arbitral panel (having some but not all the features). It does not have ...
performance bond and contract sum1/19/2012Ashish Gurav
  Q: What happens to the performance bond premium factored/included into the contract sum when the ...
  A: By agreeing to use 10% retention money in place of a performance bond, after award of work, both ...
Rights of the employer regarding Claim matter1/19/2012Senthil Kumar Sellamuthu
  Q: Good day! I am Syril, QS from Hanoi Vietnam. I have just some queries regarding claim matter. Our ...
  A: Syril, Thanks for your Questions. What ever the issues are behind, the contractor are responsible ...
Electricity / water connections to building1/18/2012Senthil Kumar Sellamuthu
  Q: Kumar I am working as construction manager in a contracting co in qatar. My question is, we are main ...
  A: Tariq, Thanks for your Questions. Normally, this type responsible should clearly mentioned in your ...
Consultant withdrwal before sustaitial completion1/18/2012Senthil Kumar Sellamuthu
  Q: In a government project, the Consultant was not paid consulting fees for 15 month, after ...
  A: Seif, Thanks for your Questions. Read the below Fidic - Client / Consultant 1998 Clauses. TIME FOR ...
Right to claim additional costs due to EoT in FIDIC 19991/18/2012Peter M. Elliott
  Q: Country: Turkey Applicable Law: Turkish law Form of Contract: FIDIC 1999 Dear Peter, In case of en ...
  A: Consequential loss is a common law concept and thus might not be applicable in this case; one of the ...
Rate Enhancement1/17/2012Peter M. Elliott
  Q: A Contractor made an unforeseen physical conditions claim under an Infrastructural Works Contract ...
  A: From the extra information, it appears that the Engineer probably has the rights of the case, but he ...
Rate Enhancement1/17/2012Peter M. Elliott
  Q: A Contractor made an unforeseen physical conditions claim under an Infrastructural Works Contract ...
  A: If we have a re-measurment contract, then it is possible that the Contractor has a valid comment, ...
hadis1/17/2012ALI IRVALI
  Q: What is hadis
  A: Hadis is a religious term of Islam. The Hadis (Hadith) is the record of the sayings of Prophet ...
BOQ Item price/amount allocated to Provisional Sum1/17/2012Senthil Kumar Sellamuthu
  Q: Under fidic 1999, for a fixed priced lump sum contract, What if the Contractor put notation on all ...
  A: Jaime, In that above case, the contractor can not get as a provisional Items for "Furnishing ...
Contract law1/17/2012Bogdan Oprea
  Q: A Contract under FIDIC MDB version 2006 for construction of a highway.The Particulat Conditions of ...
  A: In order to answer to your question I assume that the provisions of the Sub-clause 1.5 remain ...
BOQ Item price/amount allocated to Provisional Sum1/17/2012Senthil Kumar Sellamuthu
  Q: Under fidic 1999, for a fixed priced lump sum contract, What if the Contractor put notation on all ...
  A: Jaime, Thanks for your Questions. I think your understanding is not correct. "Under fidic 1999, ...
Feasability study1/17/2012Florin NICULESCU
  Q: please advice me how to do the Feasability study for a new construction project, what are the main ...
  A: Obviously, I can not give a full course on how to prepare a Feasibility Study within the context of ...
variation and additional work1/17/2012Senthil Kumar Sellamuthu
  Q: what is the diffrence between Variation and additionl work? how and where to do the value ...
  A: Qassim, The Variations are basically described from the contracts documents like Drawings, ...
Discrepancy1/17/2012Senthil Kumar Sellamuthu
  Q: if any discripancy occure in the contract between drawings, BOQ, Specification & Method Statement, ...
  A: Qassim, Thanks for your Queries. 1. I did not get you, how the big discrepancy are availing because ...
Discrepancy1/16/2012Senthil Kumar Sellamuthu
  Q: if any discripancy occure in the contract between drawings, BOQ, Specification & Method Statement, ...
  A: Qassim, Thanks for your Questions. If, you have any discrepancy with the Contract Drawing to ...
LIBOR application1/16/2012Daniel Kazado
  Q: The amount due to the contractor under any interim payment certificate issued by the engineer ...
  A: As it is stated in the contract, LIBOR+2% per annum, you shall use the annual (yearly values ) of ...
Claims1/16/2012ALI IRVALI
  Q: The project is widening and improvement of road and the contract is based on FIDIC 1987, reprinted ...
  A: In case of non-payment of any due amount under Contract, your initial proceeding may be claim the ...
Fidic 1999 - Engineer's Instructions1/16/2012Alina Valentina Oprea
  Q: Under a FIDIC 1999 Contract, the Engineer used to issue letters, drawings, and responses to the ...
  A: I did not encounter very often such case - generally, the Engineers like to instruct and command - ...
Force Majeure1/16/2012Alina Valentina Oprea
  Q: One of the nearest and major quarries for crushed stone near to site has stopped production ...
  A: In case it was not specified in the contract or in the tender that the sources of the crushed stone ...
DELAY PANALTY TO SUB CONTRACTOR1/15/2012Senthil Kumar Sellamuthu
  Q: Sir, im working for contracting company in qatar, my project based on qatar condition of contract, ...
  A: Fira, Please go through the following Clauses 15 - Default of Contractor: Sub Clause - 15.1-Notice ...
DELAY PANALTY TO SUB CONTRACTOR1/15/2012Senthil Kumar Sellamuthu
  Q: Sir, im working for contracting company in qatar, my project based on qatar condition of contract, ...
  A: Fira, Thanks for your Questions. There is no specific formula for this above delay penalty for your ...
Calling on Performance Bond1/15/2012John Dowse
  Q: "Dear John, Under Fidic 1987 contract; what is the proper procedure by the Employer for a rightful ...
  A: Presently I am in the UAE (until 25 January 2012) and can meet if desirable. Regarding your query, ...
B.O.Q PROSUM1/12/2012John Dowse
  Q: HOW CLAIM PROVISIONAL SUM EXCEED THAN MENTIONED IN B.O.Q..?
  A: Provisional sums are usually expended at the instruction of the project Engineer (or Contract ...
Drawings, Specifications & BOQ1/12/2012Peter M. Elliott
  Q: Peter I am in a situation where the client has provided all the drawings & in both drawings & BOQ ...
  A: My apologies, but, in my haste, I leapt to a solution without answering your query. If the ...
Partial Omission of Work1/11/2012Peter M. Elliott
  Q: Our project is a lump sum contract to construct a high rise building based on FIDIC 1999, we are the ...
  A: My apologies for the delayed response. You do not mention the form of contract so the following ...
Contract Claim1/11/2012Senthil Kumar Sellamuthu
  Q: We have a signed contract and the value of the contract has been reduced by approximate. 60% after ...
  A: Tariq, Refer the Fidic 1987 - Clause 52.2 - Power of Engineer to fix rates - Provided that if the ...
Contract Claim1/11/2012Senthil Kumar Sellamuthu
  Q: We have a signed contract and the value of the contract has been reduced by approximate. 60% after ...
  A: Tariq, Thanks for your Questions. Refer to your above queries you did not mentioned your contacts ...
Fidic Red Book Release of Retention1/11/2012Peter M. Elliott
  Q: I represent the employer. The contractor terminated the contract for cause. The employer had taken ...
  A: You do not say which version of the Red Book you are using so the following comments are based on ...
Release of retention sums1/11/2012Liaqat Hayat
  Q: I represent the employer. The contractor has terminated the contract under sub-clause 16.2. Do I ...
  A: Sorry for delayed response which is due to some internet problem. May i respond to your four ...

Page:   Prev  |  1  |  2  |  3  |  4  |  5  |  6  |  7  | 8  |  9  |  10   |  Next

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


Senthil Kumar Sellamuthu

Top Expert on this page

Expertise

I gained very good working and practicing knowledge in FIDIC 87 reprinted 92,99, Sub-contract 1994, Civil code of the State of the United Arab Emirates, Qatar Petroleum Contracts and Qatar Public Works Dept. Contracts. I will be answer Pre / Post tender Contractual Analysis, Cost and Time Analysis, Delay / Risk Analysis, Conditions of Contract related Issues to lies within the above mentioned type of contracts forms. I Can not answer other than Gulf Construction Laws / Contractual issues.

Experience

I have 15+ years working experience with Contracts, Consultancy & Project Management encompassing Estimation & Costing, Quantity Surveying, Project Monitoring & Execution, Techno-Commercial Operations, Cost Control, Site Administration and Relationship Management. Expertise in Commercial & Contractual matters, Quantity Surveying, Valuations, Variations, Budget & Cost Control and Project Claims, Final accounts, Contract administration and Material management.

Organizations
1. IQSA - UAE 2. AACEI - USA 3. RICS - UAE 4. DSE - UAE 5. QSi Member - UK 5. Profile in linkedin.com - http://www.linkedin.com/pub/senthil-kumar/4/6b9/700 [ Edit ]

Education/Credentials
1. Civil Engineering Professional 2. QSi Membership 3. AACEI - Certified Cost Engineer Membership 4. MRICS Professional (On going) 5. MBA (Operation Management) - On going

Awards and Honors
1. Associate Membership from AMIE - Calcutta - India 2. Certified Cost Engineer from AACEI - USA 3. Membership from QS International - UK

Past/Present Clients
1. Al Jaber Engineering - Qatar 2. Morganti Project Management INC - UAE 3. Dar Al Handasah Consultant - UAE 4. Al Shafar General Contracting - UAE 5. ETA - ASCON - UAE 6. C.T.R. & Co., - India

©2012 About.com, a part of The New York Times Company. All rights reserved.