Question
could you please direct me in step by step bases how to make/create a Recovery plan using (primavera P6) software, and followed by preparation of Action plan. Please I dont need theoretical informations, i need the practical implemented steps in such case.
thank you.

Answer

Dear Abdullah,

I have recently answered this question to some one else also but for your info i would repeat.

Please do the following steps.let say u have last updated file of 15 nov,2012 and you want that recovery plan should be created and with data update of 15th dec,2012

1.      Apply global  changes(planned start = start) in the LIVE file (always make a copy and Export XER of the schedule  for your record before applying any global change).   

2.   Make a copy of the Live File (Data Date:15th Nov 2012). The copied one will be Live File
      for us from now on (where we shall change the data date to  say for example 15th
      Dec,2012)
3.   Go to baseline and Maintain Baseline by choosing first option (i.e. save a copy of the
      current project as a new baseline).
4.   Start updating the LIVE File (DD=15th Dec 2012).and make changes as required.

After doing this i hope you would have no problem In Shaa Allah,

If still have any problem.let me know

Planning with Primavera

All Answers


Answers by Expert:


Ask Experts

Volunteer


Muhammad Taimoor Alam

Expertise

Questions related to technical tools of primavera, resource loading, cost loading, preparing and monitoring the baselines, contractual correspondence linked to primavera, how to use custom ideas in the programs. Most important is the link between the activities as per given specs and preparation of claim as per Contract FIDIC linked with plan on primavera Plus question related to contracts, regarding claims specially associated with time extension, taxation,deductions on Payment certificates can be entertained.Also questions related to Primaver 6 are entertained.

Experience

Experience in high rise buildings planning,contract, execution and technical data of the material to be used at site.And some knowledge about the design of structures. Some experince in roads as well

Organizations
Worked with five multinational firms.And on high Rise Building project.Currently on a water transmission project in KSA.

Education/Credentials
BSC in Civil Engineering Certified PMP(project management Professional from PMI) Certified PMI-SP (Scheduling Professional from PMI)

Awards and Honors
Project Management professional (PMP-PMI) Scheduling Professional (PMI -SP) Member of Pakistan Engineering Council (MPEC)

©2016 About.com. All rights reserved.