Assalama alaikum,

Sir please guide me to make high rise tower schedule. how to decide Manpower ?? is there any thumb rule ( like per sqft).it would be helpful if you give sample XER file of any highrise tower.


Syed Mushahid

W salam

Dear Mushahid,

In order to decide manpower u need some experience /information of the site works.

There are thumb rules , per sft labor cost, crew production rates and many other.this varies from industry to industry and location to location.

Manpower is generally decided (as we go for critical path method instead of Critical Chain method) once we refine our schedule based on Schedule compression techniques ( Crashing, fast tracking, lags ,leads etc).

Generally for time schedule following these steps.

- Define activities (list activities).
- Sequence activities
- Estimate activity resources( activity wise resource requirement)
- Estimate activity duration.
- Develop schedule


Planning with Primavera

All Answers

Answers by Expert:

Ask Experts


Muhammad Taimoor Alam


Questions related to technical tools of primavera, resource loading, cost loading, preparing and monitoring the baselines, contractual correspondence linked to primavera, how to use custom ideas in the programs. Most important is the link between the activities as per given specs and preparation of claim as per Contract FIDIC linked with plan on primavera Plus question related to contracts, regarding claims specially associated with time extension, taxation,deductions on Payment certificates can be entertained.Also questions related to Primaver 6 are entertained.


Experience in high rise buildings planning,contract, execution and technical data of the material to be used at site.And some knowledge about the design of structures. Some experince in roads as well

Worked with five multinational firms.And on high Rise Building project.Currently on a water transmission project in KSA.

BSC in Civil Engineering Certified PMP(project management Professional from PMI) Certified PMI-SP (Scheduling Professional from PMI)

Awards and Honors
Project Management professional (PMP-PMI) Scheduling Professional (PMI -SP) Member of Pakistan Engineering Council (MPEC)

©2016 All rights reserved.