Question
hi...
     I was given a baseline program of a project which was suppose to finished by February 2013, But due to some delays they couldn't, and the project was divided into A,B,C,D,E,F,G,H,I,J,K,L, it's original duration was DEC 14 2010 To Feb 2 2013.......  And i was told to extend the time to extend FEB 1 2015, how do i go about it?

Best regards!

Answer
Dear Ibrahim,

Thanks for your question.

1- set up the data date /progress date (till this date u have to insert actuals in the program).

2 - Then you will play with remaining durations to reach the required date feb 2015.please dont forget to apply global change start= planned start, finish= planned  finish.

the bove the procedure of prepared a revised schedule keeping in mind sthe EOT date is approved.

thanks

taimoor

Planning with Primavera

All Answers


Answers by Expert:


Ask Experts

Volunteer


Muhammad Taimoor Alam

Expertise

Questions related to technical tools of primavera, resource loading, cost loading, preparing and monitoring the baselines, contractual correspondence linked to primavera, how to use custom ideas in the programs. Most important is the link between the activities as per given specs and preparation of claim as per Contract FIDIC linked with plan on primavera Plus question related to contracts, regarding claims specially associated with time extension, taxation,deductions on Payment certificates can be entertained.Also questions related to Primaver 6 are entertained.

Experience

Experience in high rise buildings planning,contract, execution and technical data of the material to be used at site.And some knowledge about the design of structures. Some experince in roads as well

Organizations
Worked with five multinational firms.And on high Rise Building project.Currently on a water transmission project in KSA.

Education/Credentials
BSC in Civil Engineering Certified PMP(project management Professional from PMI) Certified PMI-SP (Scheduling Professional from PMI)

Awards and Honors
Project Management professional (PMP-PMI) Scheduling Professional (PMI -SP) Member of Pakistan Engineering Council (MPEC)

©2016 About.com. All rights reserved.