Planning with Primavera/Delays in primavera


I have following questions
1.I have developed a construction project plan(planned start is 10th April'13,actual start is 7th July'13. i updated the progress today and scheduled (data date)with today's  date.
i would like to know what is the delay in the project as of now?

Dear Anil,

Thanks for your questions. i understand that before updating the schedule , you have save the baseline and assigned also.

once you updated the schedule and data date is same of today.Run the schedule. and insert column s like early finish date and finish dates to see the variance.or u can insert column variance finish dates as u like.

if things are not clear please come back.



Planning with Primavera

All Answers

Answers by Expert:

Ask Experts


Muhammad Taimoor Alam


Questions related to technical tools of primavera, resource loading, cost loading, preparing and monitoring the baselines, contractual correspondence linked to primavera, how to use custom ideas in the programs. Most important is the link between the activities as per given specs and preparation of claim as per Contract FIDIC linked with plan on primavera Plus question related to contracts, regarding claims specially associated with time extension, taxation,deductions on Payment certificates can be entertained.Also questions related to Primaver 6 are entertained.


Experience in high rise buildings planning,contract, execution and technical data of the material to be used at site.And some knowledge about the design of structures. Some experince in roads as well

Worked with five multinational firms.And on high Rise Building project.Currently on a water transmission project in KSA.

BSC in Civil Engineering Certified PMP(project management Professional from PMI) Certified PMI-SP (Scheduling Professional from PMI)

Awards and Honors
Project Management professional (PMP-PMI) Scheduling Professional (PMI -SP) Member of Pakistan Engineering Council (MPEC)

©2016 All rights reserved.