Planning with Primavera/EOT for additional works

Advertisement


Question
Sir,
How to develop EOT claim by using P6 for additional woks/change in the specs/hold on activities

Anil

Answer
Dear Anil,

Thanks for your question.As per my understanding the answer can be replied in the following sections:


1- EOT for on Hold activities. Lets say an activity was on hold from 1st may upto 31st Aug. you will have the updated schedule.From 1st may you will suspend the activity until 31st aug. Update the schedule as per project progress upto 31st aug and keeping the on Hold activity suspended. Run the schedule to see the how much impact this suspension has caused on the project completion date. The same will be the days of EOT.

Compare it with your original baseline bars so one can easily understand.Please make sure that you can only two open ended activities for the baseline schedule and so you have not change the linkages while making EOT claim schedule.

2- EOT for Quantity variation. Suppose you have 300 meters of cable laying activity and in the agreed baseline you have assigned 50 days duration for this. now the quantity becomes 600 meters so you can double the duration as 100 days based on your agreed baseline schedule.

3- EOT for Additional works. simply add the activities for the new works.now if your are planning to do the additional works in parallel to original scope  then you can ask for extra cost for supervision etc.secondly, you can start the extra work after completion of the originals scope of work and that will give you the EOT time.

Please go through the above and let me know if its not clear to you.

Best Regards,

Taimoor  

Planning with Primavera

All Answers


Answers by Expert:


Ask Experts

Volunteer


Muhammad Taimoor Alam

Expertise

Questions related to technical tools of primavera, resource loading, cost loading, preparing and monitoring the baselines, contractual correspondence linked to primavera, how to use custom ideas in the programs. Most important is the link between the activities as per given specs and preparation of claim as per Contract FIDIC linked with plan on primavera Plus question related to contracts, regarding claims specially associated with time extension, taxation,deductions on Payment certificates can be entertained.Also questions related to Primaver 6 are entertained.

Experience

Experience in high rise buildings planning,contract, execution and technical data of the material to be used at site.And some knowledge about the design of structures. Some experince in roads as well

Organizations
Worked with five multinational firms.And on high Rise Building project.Currently on a water transmission project in KSA.

Education/Credentials
BSC in Civil Engineering Certified PMP(project management Professional from PMI) Certified PMI-SP (Scheduling Professional from PMI)

Awards and Honors
Project Management professional (PMP-PMI) Scheduling Professional (PMI -SP) Member of Pakistan Engineering Council (MPEC)

©2016 About.com. All rights reserved.